Mississauga, Ontario · Decks

Mississauga deck permit: when you need one and what to submit

City fee
$244
Review time
Pre-screening takes 7 to 10 business days, then the first review of a complete house application takes 10.

The City's sample drawing shows concrete piers at least 1,200 mm below grade and a ledger lag-bolted into a solid foundation wall. Plans also have to show the soil bearing capacity and guard heights.

What an application usually includes

Mississauga’s checklist has the exact list; apply through City of Mississauga ePlans.

  • A site plan with the lot lines, the house and the deck, with distances
  • A framing plan: joists, beams, posts and footings with sizes and spacing
  • Elevations and sections: guard, stairs, the ledger connection and footing depth
  • The application form and the owner or designer declaration

Local quirks

  • ePlans wants unlocked greyscale PDFs, one drawing per file, each named to match its title block.
  • Resubmissions have no guaranteed review time, and each round can add two weeks or more.

Design your Mississauga deck to the Building Code.

The design, drawings and code checks work in Mississauga today. Mississauga’s own forms aren’t built in yet, so you’ll fill those in on the City’s portal.