Do you need a permit for a deck in Ontario?

The short answer

Usually yes, if any part of the deck is more than about 600 mm (24 in) above the ground or it has a roof. Some cities also count decks attached to the house or over a set area. Permit or not, every deck has to meet the Ontario Building Code.

Last verified 2026-10-06

What the Building Code checks

  • Guards on any side more than 600 mm up: 900 mm high, or 1,070 mm above 1.8 m.
  • Footings 1.2 m deep, below the frost line.
  • Stairs with 125–200 mm risers and a handrail over three risers.
  • A roof, hot tub or privacy wall adds loads that need an engineered design.

Decks by city

The local rule and fee, linked to each City’s own source.

CityRuleFeeChecked
KitchenerYes, if the deck is more than 24 in (610 mm) above the ground or has a roof.$95 flat fee2026-10-06
WaterlooYes, if the deck is more than 24 in (610 mm) above the ground or has a roof.$132 flat fee2026-10-06
TorontoYes, if the deck is more than 60 cm (24 in) above the ground. The City's deck guide says only some detached decks can skip a permit, so plan on one for a deck attached to the house.$214.79 flat fee2026-10-07
OttawaYes, if the deck is attached to or next to the house and more than 600 mm (24 in) above the ground, or if it's a raised deck that's the main way into the house.$12.75 per $1,000 of construction value, minimum $1172026-10-07
MississaugaYes, if the deck is more than 0.61 m (2 ft) above the ground, or it's a covered porch.$2442026-10-07
BramptonYes, if the deck is attached to the house at any height, or 0.6 m (2 ft) or more above the ground.$326.21 flat fee2026-10-07
HamiltonYes for any deck attached to the house, whatever its size or height, and for a deck used with a pool.$5.36 per m² of deck, minimum $2912026-10-07
LondonYes, if the deck is more than 600 mm (2 ft) above the ground, or attached to the house at any height.$260.37, or $368.85 if it holds up a roof2026-10-07
OakvilleYes for any deck attached to the house. A freestanding deck needs one if it's bigger than 10 m² and more than 61 cm above the ground.$2202026-10-06
CambridgeCambridge gives no deck height rule. It needs a permit for any structure bigger than 10 m² (108 sq ft), which covers most decks.$143 ($118 permit plus a $25 zoning review)2026-10-07
GuelphYes, if any part of the deck floor is 0.6 m (24 in) or more above finished grade, attached or not.$160 flat fee2026-10-07

What you’ll submit

  • A site plan with the lot lines, the house and the deck, with distances
  • A framing plan: joists, beams, posts and footings with sizes and spacing
  • Elevations and sections: guard, stairs, the ledger connection and footing depth
  • The application form and the owner or designer declaration

Common questions

From the guide: Ontario deck rules, in plain English

How high does a deck railing need to be in Ontario?

900 mm if the deck is no more than 1.8 m above the ground, 1,070 mm if it's higher. A guard is required on any side more than 600 mm above the ground.

How deep do deck footings need to be in Ontario?

At least 1.2 m below finished ground, on undisturbed soil, so frost can't lift them.

Are horizontal deck railings allowed in Ontario?

Not on a required guard. Horizontal rails are climbable, and the code doesn't allow anything that helps a child climb between 140 mm and 900 mm above the deck.

Can I use deck blocks in Ontario?

Only for a small, low, freestanding, uncovered deck: up to 55 m² with joists no more than 600 mm above the ground.

What stair rise is allowed for a deck?

Each riser is 125–200 mm, and all risers are within 5 mm of each other. Runs are 255–355 mm.